Murra Wurra Wind Farm Stage 1
RES, Squadron Energy
Wind (full converter)
226 MW
– R2 testing
– Generator compliance program
– Fixed non-compliant power ramps

Crowlands wind farm
Pacific Hydro
Wind
80 MW
– Model editing
– R2 testing

LaTrobe University Solar and BESS
Enhar, NGE Electrical
Solar + BESS
4.95 MVA
Full grid connection service

Cullerin Range Wind Farm
EDL
Wind
30 MW
Islanding studies for connection application

Newstead Solar Farm
Flow Energy
Solar + BESS
4.95 MVA
Full grid connection service

Lincoln Gap Wind Farm Stage 1
Nexif Energy, Ratch SA
Wind (full converter)
126 MW
– R2 testing
– Fixed non-compliant power ramps
– Power quality test & remediation

Peterborough Solar and BESS
Birdwood Energy
BESS retrofit
4.98 MVA
– Full grid connection service
– GPS studies

Mobilong Solar Farm
Birdwood Energy
Solar + BESS
4.95 MVA
Connection application studies

ACM biogas plant
Australian Consolidated Milk
Biogas / synchronous machine
1.5 MW
– Full connection service
– Model writing
bottom of page